News

Church Lane Closure

Church Lane Closure

You may already be aware that National Grid has previously been upgrading the gas pipes around Darley Abbey and in order to complete the works there is a small section to replace on Church Lane.   The work will start on Monday 3rd February 2014 and is expected to last approximately 3 weeks.

The work will be completed in 3 phases:

Phase 1 – 3rd February – 9th February:  3-way traffic lights on Church Lane at the junction of South Avenue
Phase 2 – 10th February – 14th February:  2-way traffic lights opposite 29 Church Lane to opposite 41 Church Lane
Phase 3 – 15th February – 23rd February:  Road closure and 4-way traffic lights from outside 41 Church Lane to Abbey Lane.  During this period it will also be necessary to restrict parking to enable the flow of traffic.

There will be a diversion route in place.  Access to properties will be maintained during phases 1 and 2.  However, during phase 3 access to 43 through to 67 will be restricted, the best route will be via the diversion route which will be via Duffield Road, Mile Ash Lane, Abbey Lane and Church Lane.

If you have a gas supply to your property, you may have already received a letter from us advising how the works will affect you.    If you have not received a letter or you've got any questions please call us on 0800 0965678.

<< Back

 
 
 
Close